Article in NSC Nov/Dec 2014
Big is best for logistics centre
A large multi-spanned logistics centre has fully utilised steel’s numerous attributes.
Miller Developments, in partnership with KUC Properties are developers for this £1bn scheme that will create thousands of jobs on site. The partnership, known as Omega Warrington, has recently gained outline planning consent for further manufacturing and logistics space that will almost double the size of the current development.
As with the vast majority of distribution and logistics centres, this is a steel-framed structure and one that required steelwork contractor Caunton Engineering, working on behalf of main contractor Sir Robert McAlpine, to erect 2,100t of steel during an eight-week programme.
Steelwork was erected using three 50t capacity mobile cranes, eight MEWPs, two telehandlers for loading materials and a total of 13 erecting personnel. Caunton’s erection team had a firm cement/lime stabilised platform to work off of as the main contractor had previously undertaken a ground improvements programme as well as installing the pad foundations.
“Designing the bracing for the walls was a challenge as there are a lot of openings which had to be avoided. However there were no such restrictions in the roof and we were able to put as much bracing there as necessary,” says Pete Clayton, Caunton Engineering Contracts Manager.
Working from one end of the main 350m-long elevation, Caunton erected the steel frame portal by portal. However, due to the phased handover sequence required by the client, a considerable amount of temporary bracing was needed to allow cladding to commence before the frame was completed. Once the main frame was up Caunton had to erect attached office blocks and unloading dock canopies to the front and back elevations.
“Both of the two-storey office blocks are compositely designed as large lean-to’s getting all of their stability from the adjoining warehouse,” says Mr Clayton.
Geoff Cooper, Travis Perkins Group Chief Executive says: “This is an exciting time for the entire group. We are growing our already extensive product portfolio, and our new logistics centre in Warrington will enhance our offering by improving the supply of products to our branch network.”
The Travis Perkins Group logistics centre is scheduled to be operational by early 2015.
|
'Architect' |
Chetwoods |
|
'Structural Engineer' |
Curtins Consulting |
|
'Steelwork Contractor' |
Caunton Engineering |
|
'Main Contractor' |
Sir Robert McAlpine |
|
'Main Client' |
Travis Perkins Group |