The warehouse building with offices to the front elevation, was built in 2000. The floor area is 3,320m2. The original building was brick-clad on three sides with full height curtain walling to the front.
The brief SEGRO gave to the main contractor, Francis Construction, was to reuse as much as possible of the original building and the project must cost less than an equivalent new build. The relocation was complicated by the fact that the building required to be ‘flipped’ from its original layout to suit new access requirements at the new location.
In addition to the steel structure, the glazing, staircases, loading doors, the precast beams and planks, the curtain walling, fencing, lift and balustrading were all reused in the new, relocated building.
The project was completed in 56 weeks.
The carbon saving associated with this project was quantified by Sturgis Carbon Profiling (SCP) who concluded that the relocated building represented:
- 56% less embodied carbon at practical completion compared to a comparative New Build.
- 25% saving in costs compared to an equivalent New Build.
The project was Highly Commended in the Constructing Excellence 2015 awards.