Article in NSC November 2017
A steel-framed solution, offering a cost-efficient and quick construction programme, was the answer for a new council HQ and car park in Colwyn Bay.
By Martin Cooper
Work is under way on a new steel-framed civic building in Colwyn Bay town centre, North Wales, which will provide the local authority with a four-storey, BREEAM ‘Excellent’ headquarters. Providing 9,200m2 of office space, it will accommodate around 750 staff and replace up to 13 existing offices. The scheme also includes an adjacent three-level, 354-space car park, which is also a steel-framed structure. Overall, the scheme will contribute to the Council’s continued regeneration of Colwyn Bay, having already invested over £50M in recent years for the modernisation of the promenade, as well as extensive coastal defences.
Regeneration specialist Muse gained planning approval for the project in August 2016. The company was selected as the Council’s preferred development partner in September 2015 following a competitive procurement process. Main contractor Bowmer & Kirkland’s early involvement in the project began with a look at the design’s framing solutions. “Originally the frame was concrete for the car park and office cores, however through value engineering and a desire for cost savings the scheme switched to a full steel frame during the final design stage,” says says Bowmer & Kirkland Project Manager Mark Hooson.
“The large spans in the office and car park lend themselves to a steel solution. The use of cellular beams ensures sufficient space to distribute services within the ceiling voids,” adds AHR Associate Director Geoff Goodman. “Steel is also the most efficient and lightweight structural solution to realise the building’s very distinct roof form and glazed atrium roof, and steel also brings the benefit of programme savings through its speed of construction.”
The steel design of the car park is based around a 7.5m × 16m grid pattern, using Westok cellular beams supporting precast planks. The car park has three floors, including an open rooftop level. In order to accommodate the footprint’s slope, the middle floor has a split level. “Planning dictated that the car park structure’s height had to be kept to a certain height and so all of the beams are a maximum 575mm deep,” explains Blue Print Engineers’ (the company detailing the steelwork for EvadX) Paul Dean. “This size of beam is sufficient to create the required headroom clearance, form the long 16m span, support the planks and 75mm floor topping, and create a light airy environment because of the cellular holes that allow light into the inner parts of the building.”
Although the adjacent steel-framed office block is linked to the car park at ground floor, both buildings are structurally independent.
Kloeckner Westok provided value engineering design services to EvadX for the scheme’s clear span solution. Kloeckner’s Design Team Manager John Callanan said: “We were delighted to work with EvadX to realise the economic clear spans required for the project. Considering the strict beam depth limits throughout the structures, pre-cambered Westok cellular beams ticked all the boxes.”
Positioned in the middle of the building is an atrium, creating a full-height void that is topped with a glazed roof. Allowing natural light to penetrate the inner areas of the building, the atrium also accommodates stairs and a lift core. Supporting the atrium’s glazing is a series of 10 × 15m-long tubular bowstring trusses that span the void at roof level.
The main elevations of the office structures feature steep pitched roofs, mimicking and in keeping with the town’s 19th Century buildings. The pitched roofs are formed with propped rafters from the flat low level roof on the inner portions of the building. The outer sides are supported with perimeter columns along the outer elevations. These outer columns are either full-height or start at third floor level. In total, there are 12 pitched roofs, one atrium roof and also a high level flat roof above the main lift and stair core area.
Summing up, Muse Development Director Phil Marsden says: “This is a very important project for Colwyn Bay and the ongoing regeneration of the town. We’re working closely with Conwy Council to develop the scheme which will help them to operate more efficiently and reduce their carbon footprint by bringing a number of key services together into one energy-efficient and accessible building.” Cllr Dilwyn Roberts, Leader of Conwy County Borough Council, adds: “This new office building will not only help to streamline our office accommodation, but it’s also a key part of our regeneration programme.”
|
Architect |
AHR Architects |
|
Structural Engineer |
Arup |
|
Steelwork Contractor |
EvadX |
|
Main Contractor |
Bowmer & Kirkland |
|
Developer |
Muse Developments |
|
Main Client |
Conwy County Council |